Our Self Build Conservatory Project |
|
We are
David and Allison and we decided it a good idea to build our own Victorian
style conservatory,
after lots of research we decide to go for a high quality building:
All the drainage services that run under the conservatory site mean a steel base is the best option rather than digging footings and bridging all those pipes. To get the optimum use of the space available we decided a bespoke size would be better than an "off the shelf" size. We ordered everything from ROC Wales who manufacture the steel base and dwarf wall, they sourced the actual conservatory from Centurion DIY Conservatories. These web pages are a diary of the project, when we have remembered we have taken pictures to illustrate progress. |
|
| The ROC Steel Base Arrives but it has been manufactured wrong | 23 Dec 2005 |
| Installing the Concrete Pads a great way to work off that Christmas excess! | 27 Dec 2005 |
| Ready for the Base levelling the site and suppressing vegetation growth | 07 Jan 2006 |
| Fitting the Steel Base | 15 Jan 2006 |
| Deliveries | 20 Jan 2006 |
| Jewson the delivery that ROC forgot to organise arrives | 23 Jan 2006 |
| The Build Commences the flooring and insulation are fitted | 24 Jan 2006 |
| Dwarf Wall | 25 Jan 2006 |
| First Cut | 26 Jan 2006 |
| Frames Up | 28 Jan 2006 |
| Seal and Screw | 29 Jan 2006 |
| The Ridge | 31 Jan 2006 |
| Mortar Grinding | 01 Feb 2006 |
| Lead Flashing | 02 Feb 2006 |
| Glazing | 03 Feb 2006 |
| Roof Sheets | 11 Feb 2006 |
| Fitting the gasket to the internally fitted windows and first meal | 12 Feb 2006 |